Description

The project involved installation of a new distillation column within a new structure, design and installation of 800+metres of service/process pipework, 10+pumps, and installation of 2 reactors, 3 storage tanks and a cooling tower

Gallery

Project Outline

Completed: 2007
Client: Chemical Industry
Location: Yorkshire

Project Scope

Our role as EPCM contractor involved multi discipline design, including process, civil structural, mechanical and control electrical.  Addison also completed the project management and planning duties, procurement of all equipment and contracts on the project and construction management of the trades on site, including CDM supervision and co-ordination.

"I’d just like to let you know how impressed I’ve been with the way your engineers have worked together with us on this project." High Performance Plastics Producer